DUNBAR 


Cement Mill





Shell repair (new section fitted)



HOPE, SHEFFIELD


Cement Mill.





Trunnion repair.



WEARDALE.


No.1 Kiln


No.2 Kiln


No.2 Kiln





3 x tyre repairs.


2 x tyre repairs.


kiln roller repair and re- machine.



NORTHFLEET.


No.4 Washdrum





trunnion repair.



RIBBLESDALE.


No. 9 mill





trunnion repair.



PADESWOOD.


No. 4 mill


No. 3 Kiln


No.1 Kiln





trunnion repair.


major shell repairs.


2 x tyre repairs.



LIMERICK .


No.1 Kiln




2 tyre cracks repaired.


EUTECTIC CO. LTD (Dublin Port Tunnel)


Herrenknecht 12.875M TBM




Assemble and weld cutting head on site.


DROGHEDA.


No. 2 Kiln, Girth Gear.


No. 2 Kiln.


Cement Mill.


No. 2 Kiln, No. 2 tyre


No. 2 Kiln, No. 2 tyre


No. 2 Kiln, No. 2 tyre


No. 2 Kiln, No. 2 tyre


Raw Mill 2.


No. 2 Kiln, Conditioner Tower





3 cracks repaired.


Summer shutdown work on grate cooler and pre-heat tower.


Trunnion repair.


7 cracks repaired.


3 cracks repaired.


3 cracks repaired.


5 cracks repaired.


Re-make outer casing.


Major repairs (255 M cracked)



ROCHESTER 


Cement Mill


No. 3 Raw Mill





trunnion repair.


2 x trunnion repairs.



SOUTHAM.


No. 6 mill


No. 6 kiln


Kiln I.D. fan





trunnion repair.


shell repairs (38 Metres)


Re-furbish impellor.



SOUTH FERRIBY .


No.3 Mill


No.4 Mill


No.2 Kiln


No. 1 Kiln





trunnion repair.


5 x dished end weld repairs.


2 x in-situ roller repairs.


Tyre support pads re-weld.



HERRENKNECHT GERMANY


(Channel Tunnel Rail Link)


8.5M tunnel boring machine.







Assemble and weld on site Kent.


ARNWAY LIMITED

CEMENT & TUNNELLING PROJECTS

COMPLETED PROJECTS March 2014